As of Tuesday, July 9th, 2013:
- New HVAC equipment is 100% installed, tested and running
- Acoustical ceiling grid installation is 95% complete
- Minor mechanical, electrical and plumbing work is continuing
- Detail work continues in Dorm Rooms, Restrooms and Shower Room
- Procurement of appliances, signage and furnishings is in process
- Low-voltage systems installation is 95% complete
- New stairwell railings installation is 90% complete
- Installation of new LED lighting fixtures is 95% complete · Carpet installation is complete · Painting is 75% complete
- Installation of new sidewalks is complete.
- The overall project remains on schedule for completion in early August